Chemical plant commissioning procedure - STEPS OF PRE-COMMISSIONING PART-8 (Boxup, Leak check & Inertization)
5.0(1)
25 learners
What you'll learn
This course includes
3.3 hours of video
Certificate of completion
Access on mobile and TV
Summary
Full Transcript
The final steps of pre-commissioning include final Boxup of pipelines and equipments and also instruments and further again leak checking of the whole loop is done. Leak checking includes holding a definite pneumatic pressure as per standards and then using soap solution to check for leaks.
The leak Checking is the final step of pre-commissioning after which the pipelines and equipments are pressurised under nitrogen to avoid corrosion and dirt accumulation in any way, if the commissioning takes longer time after pre-commissioning.